Letter by Agilitas Energy, Inc. requesting that the Department review and update its existing net metering system of assurance reservation period time frames
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Letter
National Grid's notification to all Spencer-Rutland 001 Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Spencer-Rutland Group Study members on November 22, 2022, and of the previous completion of the associated transmission system.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Letter
Notification by National Grid to all Barre-Athol 001 Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Barre-Athol Group Study members on November 21, 2022, and of the previous completion of the associated transmission system impact study, making today the
Completion Date for the Barre-Athol Group Study
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Letter
Letter of notice on behalf of Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid to all Gardner-Winchendon 001 Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Gardner-Winchendon Group Study members on November 3, 2022,
and of the previous completion of the associated transmission system impact study.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Information Request Responses
Further Amended Response to Information Request 2 of the Department’s January 28, 2022 Information Requests, by Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Letter
Company's notification to all Monson-Palmer-Longmeadow (East) 001 (“MPL-East”) Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the MPL-East Group Study members on October 19, 2022.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Letter
Notification of Massachusetts Electric Company and Nantucket Electric Company, each
d/b/a National Grid, to all Milbury-Grafton Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Milbury-Grafton Group Study members on August 9, 2022.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Letter
Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid's Completion Date Notice for the Webster-Southbridge-Charlton Group Study.
: NSTAR Electric Company d/b/a Eversource Energy : Letter
Letter on behalf of NSTAR Electric Company d/b/a Eversource Energy notifying all New Bedford Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the New Bedford Group Study members on May 11, 2022, in accordance with D.P.U. 20-75-B.
: NSTAR Electric Company d/b/a Eversource Energy : Letter
Letter on behalf of NSTAR Electric Company d/b/a Eversource Energy notifying all Cape Cod Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Plymouth Group Study members on April 25, 2022.
: NSTAR Electric Company d/b/a Eversource Energy : Letter
Notifications of NSTAR Electric Company d/b/a Eversource Energy to all Plainfield-Blandford Group Study members of its intent to submit a CIP filing to the Department of Public Utilities proposing a CIP Fee associated with the Plainfield-Blandford Group Study System Modifications.
: NSTAR Electric Company d/b/a Eversource Energy : Letter
Letter on behalf of NSTAR Electric Company d/b/a Eversource Energy notifying all Plymouth Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Plymouth Group Study members on April 19, 2022.
: NSTAR Electric Company d/b/a Eversource Energy : Letter
Notification on behalf of NSTAR Electric Company d/b/a Eversource Energy to all Dartmouth-Westport Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Freetown Group Study members on April 8, 2022.
: NSTAR Electric Company d/b/a Eversource Energy : Letter
Letter on behalf of NSTAR Electric Company d/b/a Eversource Energy notifying all Plainfield-Blandford Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Plainfield-Blandford Group Study members on April 4, 2022.
: NSTAR Electric Company d/b/a Eversource Energy : Letter
Letter on behalf of NSTAR Electric Company d/b/a Eversource Energy notifying all Freetown Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Marion-Fairhaven Group Study members on April 1, 2022, in accordance with D.P.U. 20-75-B.
: NSTAR Electric Company d/b/a Eversource Energy : Letter
Letter of NSTAR Electric Company d/b/a Eversource Energy notifying all Marion-Fairhaven Group Study members and the Department of Public Utilities of the completion of the distribution system impact studies for the Marion-Fairhaven Group Study members on March 28, 2022.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Information Request Responses
Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid's Amended Response to Information Request 2 of the Department of Public Utilities.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Letter
Notification of Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid of the completion of the distribution system impact studies for the Shutesbury Group Study members on March 15, 2022, and of the previous completion of the associated transmission system impact study.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Information Request Responses
Responses of Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid to the Department’s January 28, 2022 Information Requests. Motion for Protective Treatment of Confidential Information contained in Attachment to Information Request 3
: NSTAR Electric Company d/b/a Eversource Energy : Information Request Responses
Responses of NSTAR Electric Company d/b/a Eversource Energy to the Department of Public Utilities’ January 28, 2022 information requests. Motion for Protective Treatment of Confidential Customer information.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Information Request Responses
Responses of Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid to the Department’s Third Set of Information Requests.
Department of Public Utilities’ Third Set of Information Requests to Massachusetts Electric Company and Nantucket Electric Company each d/b/a National Grid and NSTAR Electric Company d/b/a Eversource Energy.
: Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid : Comments
Reply Comments of Massachusetts Electric Company and Nantucket Electric Company, each d/b/a National Grid Concerning its System Planning Analysis Proposal.
Letter in response to the Department of Public Utilities Docket 20-75 on the matter of solar interconnection. By Senator Marc R. Pacheco, Senator Michael D. Brady, Senator John J. Cronin, Senator Julian Cyr, Senator James B. Eldridge, Senator Michael O. Moore, Senator Susan L. Moran, Senator Michael J. Rodrigues, Senator Walter F. Timilty, Representative Brian M. Ashe, Representative Peter L. Capano, Representative Antonio F.D. Cabral, Representative Marcos A. Devers, Representative Carmine L. Gentile, Representative Christopher M. Hendricks, Representative Kathleen R. LaNantra, Representative Jack Patrick Lewis, Representative Liz Miranda, Representative Brian W. Murray, Representative Tram T. Nguyen, Representative Jacob R. Olivera, Representative Steven C. Owens, Representative Lindsay N. Sabadosa, Representative Tommy Vitolo, and Representative Steven G. Xiarhos.
Joint Reply Comments on behalf of the following individuals: Gia Mahmoud, Vice President Future of Electric, National Grid; NECEC, Jeremy McDiarmid, Vice President, Policy & Government Affairs; Kaitlin Kelly O'Neill, Northeast Director, CCSA; SEBANE, Mark Sylvia, President; SEIA, David Gahl, Senior Director of State Policy, East;
MassSolar, Mark Sandeen, President; Greg Hunt, Principal, Zero Point Development; Dan Berwick, General Manager, Development, Borrego Solar; Kelly Friend, VP, Policy and Regulatory Affairs, Nexamp; Eric Graber-Lopez, President, Bluewave Solar; Jon Mancini, Senior VP, Ameresco; Matthew Doubleday, VP Project Management, SunRaise Investments LLC; Andrew Williams, VP Corporate Affairs, Sol Systems LLC.
: Attorney General : Information Request Responses
Responses of the Office of the Attorney General to the Department’s Second Set of Information Requests to Stakeholder, Information Requests Stakeholder 2-1 and 2-2.
: Northeast Clean Energy Council, Inc. : Information Request Responses
Responses of the Northeast Clean Energy Council and The Coalition for Community Solar Access to the Department's Second Set of Information Requests to Stakeholders.
: Northeast Clean Energy Council, Inc. : Information Request Responses
Responses of the Northeast Clean Energy Council, the Coalition for Community Solar Access and the Solar Energy Industries Association to the Department's First Set of Information Requests.
: Solar Energy Business Association of New England : Information Request Responses
Joint Response of Solar Energy Business Association of New England (“SEBANE”) and MassSolar to the Department's First Set of Information Requests to Stakeholders.
Response of TJA Clean Energy, LLC, to the April 6, 2021 NSTAR Electric Company d/b/a Eversource Energy’s response to the questions issued by the Department of Public Utilities on March 23, 2021.
Reply Comments of the Northeast Clean Energy Council, Inc. on the Department's Straw Proposal Regarding Distributed Energy Resource Planning and Methods for the Assignment of Costs Associated With Distributed Generation Interconnection.
Hearing Officer Memorandum Regarding login information for the question and answer conference call scheduled in D.P.U. 20-75 for next Wednesday, November 4th at 1:00 p.m. to 2:00 p.m.